| 1/29/2026 |
HB 628
LABOR AND COMMERCE
1. Line 146, introduced, after with
strike
behind-the-meter
LABOR AND COMMERCE
2. Line 146, introduced, after of
unstrike
one megawatt
strike
three megawatts
LABOR AND COMMERCE
3. Line 148, introduced, after (i)
strike
the remainder of line 148
insert
4.5 percent for the 2026 through 2030 compliance years and (ii) five percent for the 2031
LABOR AND COMMERCE
4. After line 325, introduced
insert
No later than July 1, 2033, the Commission shall initiate a proceeding to evaluate the future availability of RECs from solar, wind, and anaerobic digestion resources of one megawatt or less located in the Commonwealth in order to meet the renewable portfolio standard requirements of subdivision C 2 and may, in its sole discretion, increase or decrease by up to one percentage point the percentage of a utility's requirements under subdivision C 2 to be met with RECs from such resources in future compliance years.
LABOR AND COMMERCE
5. At the beginning of line 522, introduced
strike
3.
insert
2.
LABOR AND COMMERCE
6. After line 524, introduced
insert
3. That a Phase II Utility, as defined in subdivision A 1 of § 56-585.1 of the Code of Virginia, may recover costs associated with any petition for cost recovery made pursuant to clause (iv) of subdivision A 6 of § 56-585.1 of the Code of Virginia that has been approved by the State Corporation Commission as of December 1, 2038, notwithstanding any time limitations on such cost recovery under subdivision A 6 of § 56-585.1 of the Code of Virginia.